Completing Tasks

Once the ID has approved the build and the Tech Review is complete, take the following steps to complete the task.

  1. Ensure that task fields include necessary information:
    • Build links are in the Final URLs field.
    • Relevant issues are noted in the Issues field.
    • Subtasks are marked appropriately or completed.
  2. Add your own total time spent on the task to the Task Management subtask. (Be sure to include any estimated time for the remaining steps within that total.)
  3. Mark the Task Management subtask complete.
  4. Add the time spent across all subtasks.
  5. Enter total time spent in the overall task Time Spent field.
  6. Set the Library Status from Task Finalization to Complete.